2009 - St Petersburg Airport: Technical Advisor to VIE - Gazprom for Their Concession Bid

 

 

  • Site visits, scope definition & interpretation of the bid documentation
  • Due diligence of the existing airport
  • Traffic forecast analysis & determination of short term future demand
  • Master planning for short term demand requirements
  • Terminal re-modelling plans to provide additional capacity
  • Peer review of previous terminal development plans (to 50mppa)
  • Sizing and concept design for new terminal & satellite  
  • Remote & contact stand calculations
  • Airside master planning
  • CAPEX & OPEX projections for 30 year concession period

 

 

 

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.